New Schools Coming to South Edmonton: What Is Funded and What Is Only Planned
South Edmonton is adding schools, but "announced" can mean very different things. Some buildings have crews on site. Some have money to be designed. Some are on a wish list that the province has not agreed to pay for. This guide sorts them by stage, using the boards' own pages and the province's Budget 2026 list, and dates each claim. Where a board has not given an opening date, it says so.
The short answer
As of 20 November 2026, south schools under construction include Edmonton Public's Glenridding Heights 7-12 and K-6 and Edmonton Catholic's St. Sophia in Cavanagh and St. Michael the Archangel in Hays Ridge, all listed for fall 2028. A Catholic high school in Windermere has planning funding only and no opening date.
Key Takeaways
- Under construction means money is committed and building has started. Planning and design funding does not, and does not guarantee a build.
- Edmonton Public and Edmonton Catholic each list south schools for fall 2028, but dates have moved before, so treat them as targets.
- Edmonton Public's new-school requests for Heritage Valley Neighbourhood 14 and Kendall are in the third year of its 2026-2029 plan. They are asks, not approvals.
- None of the four Edmonton Public schools named in the province's March 2026 announcement is in the south.
- A new school can change which school is designated for an address, so check before you buy.
What Do Planning, Design and Construction Funding Mean?
They are three separate approvals, and only the last one means a school is being built. Edmonton Catholic's 9 March 2026 announcement says planning funding does not allow construction to begin. It lets the division do site work, design and readiness so a project can move toward construction later. The province's own page says Alberta Education oversees prioritization, planning and approval, and Alberta Infrastructure leads the implementation of approved projects.
A capital plan is the first step, and it is a request. Edmonton Public's 2026-2029 plan says the division is requesting provincial funding. Its March 2026 news post says the division decides which projects go into its plan and sets priorities, while the government decides which receive funding and when.
The province's Budget 2026 list, dated 6 March 2026, is worded "if passed", and lists each project as planning or design. None of these is a promise of an opening date.
Which South Schools Are Under Construction?
Seven projects in or beside the south zones show construction on the boards' own pages as of 20 November 2026. Edmonton Public lists Glenridding Heights 7-12 and K-6, the Dr. Anne Anderson addition, and Edgemont K-9 as in construction. Edmonton Catholic's new-schools page, updated 8 September 2026, lists three K-9 schools as under construction.
| School | Board | Grades | Stage | Opening as the board states it |
|---|---|---|---|---|
| Glenridding Heights | Edmonton Public | 7-12 | Construction | Fall 2028 |
| Glenridding Heights | Edmonton Public | K-6 | Construction | Fall 2028 on the current page; the 2025 plan said fall 2029 |
| Dr. Anne Anderson addition (Heritage Valley) | Edmonton Public | 10-12 | Construction | No date given |
| Edgemont | Edmonton Public | K-9 | Construction | To be determined |
| St. Sophia, Cavanagh | Edmonton Catholic | K-9 | Under construction | Fall 2028 |
| St. Michael the Archangel, Hays Ridge | Edmonton Catholic | K-9 | Under construction | Fall 2028 |
| St. Patrick, River's Edge | Edmonton Catholic | K-9 | Under construction | Fall 2028 |
A few notes. Edmonton Public's 8 June 2026 news item says the Glenridding Heights 7-12 school is expected to open in fall 2028 and will hold more than 2,400 students.
Its 2026-2029 plan, written in 2025, gave the K-6 school as fall 2029, while the division's current page says fall 2028, so the date has moved once already. The plan also says Edgemont K-9 was first expected in fall 2027 but hit geotechnical delays, and its page still says to be determined.
Edmonton Catholic's page says St. Michael the Archangel, at 3115 Hays Ridge Drive SW, serves Hays Ridge, Chappelle, Paisley and Graydon Hill, and St. Patrick serves Edgemont, River's Edge and Stillwater. It also lists St. Genevieve in West Laurel, which it says serves the Ellerslie and Mill Woods/Meadows sectors. Edmonton Public's separate Hawks Ridge K-6 is in the Big Lake area in the northwest, not Hays Ridge.
Which South Schools Only Have Planning or Design Funding?
Two, as far as the sources show. The big one is the Edmonton Catholic high school in Windermere and Glenridding Heights. The division says it will open with room for about 1,800 students and can grow to about 2,400. Its page lists the stage as planning approved in March 2026, with next steps and opening date to be determined.
| Project | Board | Stage | Date and opening |
|---|---|---|---|
| Windermere / Glenridding Heights high school | Edmonton Catholic | Planning | Announced 9 March 2026; no opening date |
| New ECS-6 school in south Edmonton | Conseil scolaire Centre-Nord | Planning | On the Budget 2026 list dated 6 March 2026; no location or opening date given |
The second is a French-language school. The province's Budget 2026 list shows Conseil scolaire Centre-Nord with a new ECS-6 school in south Edmonton at the planning stage. The list gives no neighbourhood, so it is not possible to say which community it will serve.
On the public side, the four Edmonton Public projects in the March 2026 announcement were Aster, Stillwater, Crystallina Nera and River's Edge. The division describes them as southeast, west, north and west, so none is in the south.
Which South Schools Are Only Requested?
Edmonton Public's 2026-2029 plan asks the province for several. It lists a K-6 school in Heritage Valley Neighbourhood 14 and a K-6 school in Kendall, both in year three, plus modernizations at Brander Gardens and Keheewin.
| Project | Board and plan | Where it sits in the plan |
|---|---|---|
| Heritage Valley Neighbourhood 14, K-6 (650 students) | Edmonton Public, 2026-2029 | Year 3 new construction |
| Kendall, K-6 (650 students) | Edmonton Public, 2026-2029 | Year 3 new construction |
| Brander Gardens K-6 modernization or addition | Edmonton Public, 2026-2029 | Priority 8 of 30 |
| Keheewin K-6 modernization or addition | Edmonton Public, 2026-2029 | Priority 25 of 30 |
Newer plans exist. Edmonton Public's 2027-2030 plan, approved 14 April 2026, still has the Heritage Valley Neighbourhood 14 school in year three, with Kendall K-6 at 890 students in year three. Edmonton Catholic's 2027-2030 plan, reported 25 March 2026, names a K-9 school in Windermere (Kendal) among six projects it wants construction approval for.
We could not match that school to a provincial funding announcement, so treat it as a request. Edmonton Catholic's 2026-2029 plan, approved 19 March 2025, put the Windermere high school in year one and also asks for four K-9 schools in years two and three without naming them. Plans are renewed every year, and priorities move.
What Does a New School Mean for the Homes Around It?
It can mean a different designated school. Edmonton Public says its attendance areas may be modified when new schools open, and Edmonton Catholic has run consultations and set effective dates for boundary changes. Neither board has told us how the south areas will be drawn for the 2028 schools, and nothing in the sources says an address will or will not move. Read the guide to school catchments for how to look up an address.
It also shows where the boards expect families. Edmonton Public's plan says Glenridding Heights saw the most low-density lots added of any neighbourhood in the city. As of 20 November 2026, this site shows 23 active listings in Glenridding Heights, 14 in Cavanagh, 153 in Chappelle and 76 in Edgemont. For the wider picture, see the Heritage Valley guide and the new construction homes page.
A school that is funded can still open late. Do not make a buying decision that depends on a school opening in a given month.
What to Do Next
- Check each school's stage on the board's own page, Edmonton Public's new schools page or Edmonton Catholic's new-schools page, and note the date shown.
- Ask the board's planning team whether the address you like is likely to be affected when the nearby school opens.
- If a school matters to your timing, talk to Eddie before you make an offer.
Last reviewed 3 November 2026. This is general information, not legal, tax, mortgage or financial advice. Rules, programs and prices change, so check the current details with the City, the school board, a lawyer or a mortgage professional before you commit. Market figures use asking prices on active MLS® listings, not sales.
Sources
- Edmonton Catholic Schools, New Schools, page updated 8 September 2026, checked 20 November 2026
- Edmonton Public Schools, New schools and modernizations, checked 20 November 2026
- Edmonton Public Schools, Three-Year Capital Plan 2026-2029, 2025
- Edmonton Public Schools, Three-Year Capital Plan 2027-2030 info sheet, approved 14 April 2026
- Edmonton Public Schools, province announces funding for four new schools, 10 March 2026
- Edmonton Public Schools, construction advancing on the Glenridding Heights 7-12 school, 8 June 2026
- Government of Alberta, Budget 2026 school projects, 6 March 2026
- Government of Alberta, Planning school projects, checked 20 November 2026
- Edmonton Catholic Schools, planning funding for three new Catholic schools, 9 March 2026
- Edmonton Catholic Schools, 2026-2029 Capital Plan, 19 March 2025, and 2027-2030 Capital Plan, 25 March 2026
- Edmonton Catholic Schools, St. Carlo Acutis attendance boundary engagement and Big Lake attendance area update, December 2025
- Edmonton Public Schools, elementary attendance-area map layer, checked 20 November 2026
Your next step
Weighing a Community by Its Schools?
Eddie can show you what is listed near the sites that are funded, and tell you which board page to check before you make an offer.
Talk to EddieCommon Questions
Which new schools are being built in south Edmonton?
As of 28 October 2026, Edmonton Public lists Glenridding Heights 7-12 and K-6 and the Dr. Anne Anderson addition in construction. Edmonton Catholic lists St. Sophia in Cavanagh and St. Michael the Archangel in Hays Ridge as under construction. The boards' pages show fall 2028 for most of these.
Is the new Catholic high school in Windermere going to be built?
It is a real project but not a construction one yet. Edmonton Catholic says the province approved planning funding on 9 March 2026, which does not allow construction to begin. The board lists next steps and an opening date as to be determined, so no one can say when it will open.
What is the difference between a capital plan and a funded school?
A capital plan is a board's ranked request to the province. Edmonton Public says it decides what goes in its plan, while the government decides which projects receive funding and when. A funded school has a planning, design or construction approval, and only construction funding means a building is going up.
Will a new school change my child's designated school?
It might. Edmonton Public says attendance areas may be modified when new schools open, and Edmonton Catholic has run consultations on boundaries for new schools. We found no published south areas for the 2028 schools, so ask each board's planning team about your address.
Can I rely on a new school's opening date when I buy?
No. Dates have moved. Edmonton Public's 2025 plan gave fall 2027 for Edgemont K-9, which now shows to be determined, and fall 2029 for Glenridding Heights K-6, which now shows fall 2028. Treat any date as a board target and check the current page.